Light mortar from cinder pulverization
Light mortar from cinder pulverization
ASC, 2025.
ASC, 2025.
This had-oc material test, as the title explains, starts with cinder blocks pulverization, aiming to recycle aggregates for a new necessary lightweight mortar, but also to measure how much time does it take to pulverize with basic hand tools.
This had-oc material test, as the title explains, starts with cinder blocks pulverization, aiming to recycle aggregates for a new necessary lightweight mortar, but also to measure how much time does it take to pulverize with basic hand tools.
Volume of mortar needed: 0.8 liters = 0.0008m3
Volume of mortar needed: 0.8 liters = 0.0008m3
Desired density= 1000kg/m3
Desired density= 1000kg/m3
Dosage: 3 x 1 x Eps:
Dosage: 3 x 1 x Eps:
800g total mortar weight, of which EPS is insignificant,
800g total mortar weight, of which EPS is insignificant,
200g of cement Cp3 32rs,
200g of cement Cp3 32rs,
600g of pulv. Aggregate.
600g of pulv. Aggregate.
Timing
Timing
1. Cinder pulverization = 600 g
1. Cinder pulverization = 600 g
Time required to pulverize = 130 seconds
Time required to pulverize = 130 seconds
2. Eps foam to pearls = 400ml (a piece of 1x28 x14.3cm)
2. Eps foam to pearls = 400ml (a piece of 1x28 x14.3cm)
Time required to split pearls = 16 minutes
Time required to split pearls = 16 minutes
3. Mix:
3. Mix:
Water = 200ml, time needed: 10 minutes.
Water = 200ml, time needed: 10 minutes.